20RESB Stage 2

Last week they poured the slab

This week they actually installed the generator and associated electrical connections.

Last Week

 
  

This Week

   

    
  
   
    
 
Next week the gas company will run a second natural gas line with second meter to the generator, after which the final installation, testing, and handover will be completed. Barring anything that knocks out the gas mains, I will have electric power regardless of hurricane, ice storm, grid failure, or Zombie Apocalypse.

The purchase of this standby generator is somewhere between an extravagance and necessity. It is comforting to know that I won’t loose power in all but the most extreme system failures. The Mrs has Multiple Sclerosis and no tolerance for the summer heat of South Texas. A day or two without air conditioning would precipitate a medical emergency. It is an insurance policy that I don’t mind having to use. My neighbors are already trying to figure out how to run extension cords to my house. 🙂

2 thoughts on “20RESB Stage 2

  1. The generator came on tonight following a power failure during a rain storm (see Haiku #14). Based on email alerts from the power company, I think that the power was only out for about 10 minutes. But I don’t really know because my power was only out about 10 seconds (until the generator kicked on).

    I still need to get a UPS for my son’s computer and the cable modem though.

    Like

Leave a comment ... or else ...

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s